Quantcast
Channel: Nuclear – The Survival Place Blog
Viewing all articles
Browse latest Browse all 8

Fukushima operators begin risky nuclear fuel rod removal

$
0
0

This handout picture taken by Tokyo Electric Power Co (TEPCO) on November 18, 2013 shows a cask (C) of nuclear fuel being lifted and moved by TEPCO workers as TEPCO started operations to remove fuel rods from a pool at the unit four reactor building of TEPCO's Fukushima Dai-ichi nuclear plant in the town of Okuma in Fukushima prefecture (AFP Photo)

This handout picture taken by Tokyo Electric Power Co (TEPCO) on November 18, 2013 shows a cask (C) of nuclear fuel being lifted and moved by TEPCO workers as TEPCO started operations to remove fuel rods from a pool at the unit four reactor building of TEPCO’s Fukushima Dai-ichi nuclear plant in the town of Okuma in Fukushima prefecture (AFP Photo)

In a highly risky undertaking Fukushima plant operators have finally begun removing over 1,500 nuclear fuel rods from one of the four reactors at its damaged nuclear power plant in northeastern Japan on Monday.

The operation is expected to take at least a year hailed as a   key first step toward a full cleanup of the  plant.

Unit 4 of the Fukushima Daiichi plant was offline at the time of  the 2011 catastrophic earthquake and tsunami, which is why,  unlike the other three, its core didn’t go into meltdown.

Hydrogen explosions blew the roof off the building and severely  damaged the structure, however. Keeping so many fuel rods in a  storage pool in the building poses a serious safety risk, experts  say.

With the help of robots and cranes, the workers will attempt to  cautiously transfer 1,331 spent fuel rods and 202 new ones from  the damaged reactor pool to a more reliable storage facility. If  these rods break or overheat, radioactive gases could be released  into the atmosphere, however, prompting a self-sustained nuclear  chain reaction.

According to the operators of the plant, Tokyo Electric Power Co  (TEPCO), all necessary measures have been taken to contain the  threat stemming from the worst nuclear disaster since Chernobyl.

This handout picture taken by Tokyo Electric Power Co (TEPCO) on November 18, 2013 shows a cask (C) of nuclear fuel being lifted and moved by TEPCO workers as TEPCO started operations to remove fuel rods from a pool at the unit four reactor building of TEPCO's Fukushima Dai-ichi nuclear plant in the town of Okuma in Fukushima prefecture (AFP Photo)This handout picture taken by Tokyo Electric Power Co (TEPCO) on November 18, 2013 shows a cask (C) of nuclear fuel being lifted and moved by TEPCO workers as TEPCO started operations to remove fuel rods from a pool at the unit four reactor building of TEPCO’s Fukushima Dai-ichi nuclear plant in the town of Okuma in Fukushima prefecture (AFP Photo)

While the full decommissioning of the plant is expected to take  decades, the company said it plans to remove 22 rods over the  course of two days. A giant crane equipped with a remote-  controlled pincer will be lowered into the pool and hook onto the  rods, placing them inside a 91-ton cask which will be loaded on  to a trailer and taken to a new storage pool.

Earlier this week it was reported that three of the spent fuel  assemblies that will be pulled from the nuclear plant on Monday  were in fact damaged before the 2011 earthquake hit the facility.  TEPCO said the damaged assemblies – 4.5 meter high racks with 50  to 70 rods of highly irradiated used fuel – wouldn’t be lifted  from the plant’s Reactor No. 4, Reuters reported.

In an 11-page information sheet released in August, TEPCO  informed that one of the assemblies was actually damaged back in  1982, when it was bent out of shape during a transfer.

Japan’s Nuclear Regulation Authority has assigned an inspector to  keep an eye on the dangerous operation, as well as video  monitoring of the removal site.

Meanwhile, targets for reducing radiation levels and eradicating  nuclear fallout in the areas still haven’t been met, with the  radius of evacuation after the Fukushima nuclear meltdown larger  than the area of Hong Kong. Some areas will remain contaminated  for years to come, experts say. Part of the cleanup plan is to  decontaminate the surrounding towns and villages and follow new  guidelines by the International Center for Radiological  Protection.

Nuclear expert inspecting the unit four reactor building of the crippled TEPCO's Fukushima Dai-ichi nuclear plant at Okuma town in Fukushima prefecture (AFP Photo / TEPCO)Nuclear expert inspecting the unit four reactor building of the crippled TEPCO’s Fukushima Dai-ichi nuclear plant at Okuma town in Fukushima prefecture (AFP Photo / TEPCO)

Major setbacks have stalled TEPCO’s handling of the crisis amid  widespread criticism. The utility was scheduled to begin the  clean-up operation earlier this month which had to be put off  after the Japan Nuclear Energy Safety Organization pressed for  further safety checks.

A recent special investigation by Reuters has revealed the   distressing conditions of working at the  crippled Fukushima Daiichi plant, which are aggravated by very  low pay and questionable attitudes to workers’ rights by  sub-contractors involved in the numerous projects.

TEPCO is in the process of decommissioning the entire six-reactor  Fukushima Daiichi plant after three reactors suffered core  meltdowns in March 2011. Moving the fuel assemblies in Reactor  No. 4 remains the top priority, as their height above ground  appears to be highly vulnerable to another earthquake.  – Read more at RT

The post Fukushima operators begin risky nuclear fuel rod removal appeared first on The Survival Place Blog.


Viewing all articles
Browse latest Browse all 8

Latest Images

Trending Articles





Latest Images